What are the phases of the permitting and regulatory process for industrial hall construction in Hungary?

The realization of an industrial hall involves several regulatory and permitting steps. If the investor is aware of these right at the start of the project, delays and unexpected costs can be avoided, allowing the construction of the hall to proceed more quickly and safely.

1. Verification of Plot and Zoning Regulations


The first step of the investment is to verify whether the selected plot is suitable for constructing the envisioned hall..


Aspects to be examined:
  1. zoning classification
  2. maximum site coverage (built-in ratio)
  3. building height limits
  4. front, side, and rear yard regulations
  5. utility supply

These are generally defined by the local municipality's local building regulations (HÉSZ).

2. Preliminary Design


The concept of the building is developed during this phase.


This includes:

  1. architectural concept design
  2. site layout plan
  3. functional layout
  4. preliminary cost estimation


This stage determines whether the planned building can be implemented on the given plot.

3. Engineering and Specialist Design


Following the approval of the concept, detailed technical designs are prepared.


Typical engineering disciplines:

  1. architectural design
  2. structural design
  3. mechanical design
  4. electrical design
  5. fire safety design

4. Regulatory Permitting Process


The construction of an industrial hall is generally an activity subject to a building permit.


During the permitting process, the following are reviewed:
  1. compliance of the building with construction regulations
  2. environmental conditions
  3. fire safety requirements
  4. utility connections

The permitting documentation is evaluated by the building authority.

5. Consultation with Statutory Authorities


In certain cases, the involvement of additional authorities is required.


For example:

  1. disaster management (fire safety)
  2. road authority (road connection)
  3. utility providers
  4. environmental authority

6. Obtaining the Building Permit


Once the permit is granted, the investor is entitled to commence construction. This requires:

  1. final planning permission drawings and documents
  2. owner consents
  3. regulatory approvals

7. Preparation of Working Drawings


Detailed technical documentation is required for the execution of the construction.


This includes:

  1. detailed structural solutions
  2. material specifications
  3. detailed construction drawings

8. Commencement of Construction


Before building work begins, the following are required:


  1. selection of the contractor
  2. opening of the construction log
  3. appointment of a technical supervisor

Actual construction can then begin.

9. Technical Handover and Acceptance


Upon completion of the construction, a technical inspection of the building takes place during handover. At this stage, we are present as the contractor, alongside you as the investor and your technical supervisor.


During this process, the technical supervisor inspects:
  1. the quality of construction
  2. compliance with the designs
  3. adherence to safety regulations

10. Occupancy Permit


An occupancy permit is required for the official use of the industrial hall.

This generally requires:

  1. technical documentation
  2. certificates of completion from the contractor
  3. regulatory approvals

After obtaining the permit, the building can be commissioned and put into use.

Beruházóként milyen szempontokat kell átgondolni egy csarnok megrendelése előtt?

Összesítettük, hogy megrendelői oldalról milyen részleteket szükséges Önöknek előzetesen átgondolniuk egy beruházás előtt. Ez vonatkozik a csarnok funkcióira, a prioritásokra, a költségvetési elképzelésekre és sok egyébre. Ezek alapján lehet felelős árajánlatot készíteni illetve ezek alapján tudunk majd olyan csarnokot tervezni és építeni Önöknek, ami 100%-ban megfelel az igényeiknek.

Ellenőrző lista építési telek kiválasztásához

Ha nem az általunk kínált telkek közül szeretne választani, mindenképp javasoljuk az ellenőrző lista használatát. Egy csarnok beruházás sikere már a telekválasztásnál eldőlhet. Egy rosszul kiválasztott telek később komoly pluszköltségeket, engedélyezési problémákat és működési nehézségeket okozhat. Ellenőrző listánkkal abban szeretnénk segíteni, hogy időben átgondolják a legfontosabb szempontokat, és megalapozott döntést hozhassanak.